Introduction to MS Project 2007 - جامعة الملك سعود

Introduction to MS Project 2007 - جامعة الملك سعود

Introduction to MS Project 2007 TUTORIAL 3 I N S T R UC T O R : H A N I F UL L A H E M A I L I D: h a n i f. k s u @ h ot m a i l . c o m O F F I CE # : 2 02 9 DAT E: 1 4 / 1 0 / 2 01 2 Linking Tasks Projects require tasks to be performed in a specific order. For example, the task of filming a scene must be completed before the task of editing the filmed scene can occur. These two tasks have a finish-to-start relationship (also called a link or dependency) that has two

aspects: The second task must occur later than the first task; this is a sequence. The second task can occur only if the first task is completed; this is a dependency. Linking Tasks In Project, the first task (film the scene) is called the predecessor because it precedes tasks that depend on it. The second task (edit the filmed scene) is called the successor because it succeeds tasks on which it is dependent. Any task can be a predecessor for one or more successor tasks. Likewise, any task can be a successor to one or more predecessor tasks. Tasks can be linked in four ways:

Finish-to-Start: Predecessor finishes and the other starts Start-to-Finish: Task begins at the same time as its predecessor finishes. Finish-to-Finish: Both tasks finish at the same time. Start-to-Start: Start of the predecessor determines when the other starts. This is the default setting for any pair of tasks. Linking Tasks This task relationship Looks like this in the Gantt chart

Example Finish-to-start (FS) A film scene must be shot before it can be edited. Start-to-start (SS) Reviewing a script and developing the script breakdown and schedule are closely related, and they should occur simultaneously. Finish-to-finish (FF) Tasks that require specific equipment must end when the equipment rental ends.

Start-to-finish (SF) The time when the editing lab becomes available determines when a pre-editing task must end. (This type of relationship is rarely used.) Linking Tasks First youll create a finish-to-start dependency between two tasks. Select the names of tasks 2 and 3. On the Edit menu, click Link Tasks. Next, you will link several tasks at once. Select the names of tasks 3 through 6. On the Edit menu, click Link Tasks.

Tasks 3 through 6 are linked with a finish-tostart relationship. Linking Tasks Next, you will link two tasks in a different way by making task 8 the predecessor of task 9. Select the name of task 9. 6. On the Project menu, click Task Information. Click the Predecessors tab. 8. Click the empty cell below the Task Name column heading, and then click the down arrow that appears. 9. On the Task Name list, click Rehearse, and press Enter. Click OK to close the Task Information dialog box. Tasks 8 and 9 are linked with a finish-to-start relationship.

Linking Tasks To finalize this exercise, youll link the remaining production tasks and then link the two summary tasks. Select the names of tasks 9 and 10. On the Edit menu, click Link Tasks. Select the name of task 1 and, while holding down the Ctrl key, select the name of task 7. This is how you make a nonadjacent selection in a table in Project. On the Edit menu, click Link Tasks to link the two summary tasks. Documenting Tasks You can record additional information about a task

in a note. In this exercise, you enter task notes and hyperlinks to document important information about some tasks. Select the name of task 4, Pick locations. On the Project menu, click Task Notes. In the Notes box, type Includes exterior street scene and indoor studio scenes. Click OK. A note icon appears in the Indicators column. Point to the note icon. Documenting Tasks To conclude this exercise, you create a

hyperlink. Select the name of task 5, Hold auditions. On the Insert menu, click Hyperlink. The Insert Hyperlink dialog box appears. In the Text to display box, type Check recent agent postings In the Address box, type http://www.google.com Click OK A hyperlink icon appears in the Indicators column. Checking the Plans Duration In this exercise, you see the current total duration and scheduled finish date of the project based on the task durations and relationships youve entered. On the Project menu, click Project Information.

Note the finish date Next, lets look at the duration information in more detail. Click the Statistics button. The Project Statistics dialog box appears. You dont need to pay attention to all of these numbers yet, but the current finish date and current duration are worth noting. The duration is the number of working days in the project calendar between the projects start date and finish date. Checking the Plans Duration Next, you will display the complete project by changing the timescale in the Gantt Chart view. On the View menu, click Zoom. The Zoom dialog box appears. Click Entire project, and then click OK

The entire project appears on the screen. You can see the projects overall duration in the Gantt Chart view. Resources Resources include the people and equipment needed to complete the tasks in a project. Microsoft Office Project 2007 focuses on two aspects of resources: their availability and their costs. Availability determines when specific resources can work on tasks and how much work they can perform, and costs refer to how much money will be required to pay for those resources. In addition, Project supports two other types of special resources: material and cost. There are three main types of resources. 1. People or equipment or work resources 2. Consumable materials or material resources

3. Cost items or cost resources Setting Up Work Resources Work resources are the people and equipment that do the work of the project. Work Resource Example Individual people identified by name Jon Ganio; Jim Hance Individual people identified by job title or function

Director; camera operator Groups of people who have common skills (When Electricians; assigning such interchangeable resources to a task, do carpenters; not be concerned who the individual resource is as long extras as the resource has the right skills.) Equipment Video camera; 600-watt light Setting Up People Resources On the View menu, click Resource Sheet. In the Resource Sheet view, click the

cell directly below the Resource Name column heading. Type Jonathan Mollerup, and press Enter . Project creates a new resource. On the next empty rows in the Resource Name column, enter the following names: Jon Ganio Garrett R.Vargas John Rodman Setting Up People Resources You can also have a resource that represents multiple people. In the Resource Name field below the last resource, type Electrician, and then press Tab . In the Type field, make sure that Work is selected, and then

press Tab several times to move to the Max. Units field. The Max. Units field represents the maximum capacity of a resource to accomplish any task. Specifying that a resource, such as Jon Ganio, has 100% maximum units means that 100% of Jons time is available to work on the tasks to which you assign him. In the Max. Units field for the electrician, type or select 200%, and then press Enter. Click the Max. Units field for Jon Ganio, type or select 50%, and then press Enter. Setting Up Equipment Resources In Project, you set up people and equipment resources in exactly the same way because people and equipment are both examples of work resources. In this exercise, you enter information about equipment

resources in the Resource Information dialog box. In the Resource Sheet, click the next empty cell in the Resource Name column. On the Standard toolbar, click the Resource Information button. Click the General tab if it is not already displayed In the Resource name field, type Mini-DV Camcorder In the Type field, click Work. Setting Up Equipment Resources the Max. Units field for the Mini-DV Camcorder, type or click the arrows until the value shown is 300% and press Enter. This means that you plan to have three camcorders available every workday. Enter

the following information about equipment resources directly in the Resource Sheet or in the Resource Information dialog box, whichever you prefer. case, make Resource nameIn either Max. Units sure Work is selected in the Type field. Camera Boom 200%

In Editing Lab 100% Setting Up Material Resources Material resources are consumables that you use up as the project proceeds. On a construction project, material resources might include nails, lumber, and concrete. For the toy commercial project, video tape is the consumable resource that interests you most. In this exercise, you enter information about a material resource. In the Resource Sheet, click the next empty cell in the Resource Name column. Type Video Tape and press Tab. In the Type field, click the down arrow, select Material, and press Tab.

In the Material Label field, type 30-min. cassette and press Enter. You will use 30-minute cassettes as the unit of measure to track video tape consumption during the project. Note that you cannot enter a Max. Units value for a material resource. Since a material resource is a consumable item and not a person or piece of equipment that performs work, the Max. Units value doesnt apply. Setting Up Cost Resources You can use a cost resource to represent a financial cost associated with a task in a project. While work resources, such as people and equipment, can have associated costs (hourly rates and fixed costs per assignment), the sole purpose of a cost resource is to associate a particular type of cost with one or more tasks. Common types of cost resources might include categories

of expenses youd want to track on a project for accounting purposes such as travel, entertainment, or training. Like material resources, cost resources do no work and have no effect on the scheduling of a task. In the Resource Sheet, click the next empty cell in the Resource Name column. Type Travel and press Tab. In the Type field, click the down arrow, select Cost, and press Enter.

Recently Viewed Presentations

  • Compliments of

    Compliments of

    Point Source Outbreak In October 2005 27 Staph aureus isolates (17 MSSA and 10 MRSA) were sent to the Mayo Clinic for pulsed field gel electrophoresis These included 15 nosocomial strains and 12 community-acquired strains Purpose: To determine if we...
  •   1980   (1)  (2)  (3)   :  WTO  19989  30%

    1980 (1) (2) (3) : WTO 19989 30%

    全球化趨勢與東亞區域經濟 整合的前景. Sheet2. Sheet1. Chart6. 歐盟. 北美自由貿易區. 其他. 台、新、南韓. 東協四國. 大陸、香港
  • Efficient IT: Can OUCS Help? Dr Stuart D Lee Director ...

    Efficient IT: Can OUCS Help? Dr Stuart D Lee Director ...

    Dr Stuart D Lee Director, Computing Systems and Services OUCS [email protected] Programme OUCS: The Basics Slide 4 Slide 5 Slide 6 What we do not support Slide 8 Your local IT Officer Slide 10 What you will come away with...
  • Identity Theft Prevention Program Red Flags Rules Fighting

    Identity Theft Prevention Program Red Flags Rules Fighting

    Don't forget portable devices and offsite locations, including employees' home computers. For example, an employee emails to a personal account, or copies to USB storage, sensitive information for use while working from home. Trace the flow of information from data...
  • Skin refractive index - Eventry

    Skin refractive index - Eventry

    GLYCEROL: TERMS, PROPERTIES, CONSTANTS, FORMULAS Saratov State University Optics & Biomedical Physics Department Mikhail M. Stolnitz Saratov State University, Saratov, Russia
  • ELSA Negotiation Competition

    ELSA Negotiation Competition

    in the Negotiation Competition. Both competitions as well need to be . comparable . in regards to the simulations and the judgement criteria. The entry into the ELSA Negotiation Competition is . upon the permission. and approval by the respective...
  • Chauncy Awards Monday 20th Friday 24th January YEAR SEVEN ...

    Chauncy Awards Monday 20th Friday 24th January YEAR SEVEN ...

    YEAR SEVEN BRONZE AWARDS YEAR EIGHT BRONZE AWARDS YEAR NINE BRONZE AWARDS YEAR TEN BRONZE AWARDS None this week YEAR ELEVEN BRONZE AWARDS This academic year None this ...
  • Intelligent Agent Technology - OBJS

    Intelligent Agent Technology - OBJS

    Intelligent Agent Technology ... Voyager, Java platform enhancements) Easier creation of sophisticated agents ADT, comprised initially of CDT, SDT, PDT Deploy in spectrum of application areas Current areas: Information Access, DIG-IT, NASA Aviation Extranet, DARPA JumpStart New opportunities ...